Annexation & Development Agreement

Annexation and Development Agreement Highlights:
  • .6% of the 1% Real Estate Transfer Assessment to Town of Eagle - Estimated at approximately $12 million revenue over 40 years
  • Street Impact Fees - Total Estimate $723,000 revenue
  • Highway 6 Study - $700,000 cost
  • Construction of Brush Creek Road Extension complete within 5 years from the date of the first Final Plat or upon the issuance of the building permit for the 300th dwelling unit whichever comes first.*
  • Pre-Payment of Waster Plant Investment Fees - $3 million revenue
  • Recreation and School Site - 32 acres
  • Fire Station Site - 1.6 acres
  • Construction of Sylvan Lake Road/Brush Creek Road realignment and roundabout
For details, please see Section 10.1 Annexation and Development Agreement.